X

SUBMIT QUERY

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
X

REQUEST INFO

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

BLOG & NEWS

BACK TO BLOG

A&T Group Interiors X talabat, Behind-The-Scenes, Episode 3

March 2, 2023

We are back with our final behind-the-scenes episode which takes a look at our entire interior fit-out delivery for Talabat UAE Regional Headquarters, right from kick-off, to completion.

Question: How long does it take to build one of the Middle East's largest tech hubs, housing almost 2,000 employees?

Answer: Just over 4 months according to our critical project milestones below:

  • 09th Aug 22 - Tender award to A&T Group Interiors
  • 10th Aug 22 - Landlord & client kick-off meetings
  • 12th Aug 22 - Permit to work received [Mobilization day]
  • 29th Dec 22 - Dubai Civil Defense [DCD] completion certificate received
  • 30th Dec 22 - Final handover to the client

This giant of a commercial office space is home to 49 think tanks, 45 meeting rooms, 650+ workstations, and 15 collab areas.

We hope you enjoy this inside look at our journey to on-time delivery.

Our news and blog posts intend to keep our audience up to date with everything A&T. Via this section we strive to deliver information that provides real value to the design and construction industry. If you would like to open a conversation with us, comment or debate – please get in touch with info@atginteriors.com.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Scroll To Top